Kitchen - End of Day 4

The kitchen is coming along really well. At the end of day 4, they were able to put in all but 2 of the upper cabinets, finish the island and mount the sink base. Overall, it's looking good. Here are a few shots from this morning:









The rest of the schedule (if all goes well):

Monday, 5/21 - Electrician (outlet for wine fridge, 110 outlet behind oven)
Monday, 5/21 - Measure for countertop (hopefully)
Tuesday, 5/22 - Off (was supposed to be drywall, but we don't need it)
Wednesday, 5/23 - Mount the rest of the uppers, begin finishing
Thursday, 5/23 - Finish trim & pantry door, install appliances (except dishwasher)

Sometime about 2 weeks from now - install sink, countertop, dishwasher. BE FINISHED!